Weil-McLain Boiler: Tight construction requires outside air openings
Tight construction requires outside air openings on a Weil-McLain boiler: Buildings with continuous vapor retarder, weather-stripped openings and sealed penetrations are considered unusually tight. In these buildings, outside air openings into the building must be sized for the appliances.
Applies to: SVF 1500-3000 Series 1
How to fix tight construction requires outside air openings: step by step
- Check whether the building meets the tight construction definition in the National Fuel Gas Code.
- If tight, size outside air openings per Figure 26 or Figure 33 for the case that applies.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: Weil-McLain SVF Series 1 boiler manual, p. 32, p. 38. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.