Weil-McLain Boiler: Relief valve installation and discharge line
Relief valve installation and discharge line on a Weil-McLain boiler: Relief valve is installed vertically in the 3/4 in. tapping on the side of the boiler. A discharge line is mandatory and must follow these rules.
Applies to: EG water boilers
How to fix relief valve installation and discharge line: step by step
- Install the relief valve vertically in the 3/4 in. side tapping.
- Follow the manufacturer's tag on the valve.
- Keep the discharge line as short as possible and the same size as the valve outlet over its full length.
- Pitch the discharge line downward from the valve. End it at least 6 in. above a floor drain where discharge is visible.
- End the line plain (not threaded), rated for at least 375°F.
- Do not route the discharge where freezing can occur.
- Do not put a shutoff valve between the relief valve and boiler or in the discharge line. Do not plug or obstruct the line.
- After filling and pressurizing, test the valve by lifting the lever. Confirm it discharges freely. Replace the valve if it does not operate correctly.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
More commissioning tips for boiler
Source: EG/PEG Series 7 boiler manual, p. 20. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.