Weil-McLain Boiler: Install the termination plate before the piping and support the run
Install the termination plate before the piping and support the run on a Weil-McLain boiler: The Weil-McLain termination plate must be mounted before piping is run from the boiler to the termination. Support the piping so it stays sloped and does not sag.
Applies to: Weil-McLain sidewall termination plate
How to fix install the termination plate before the piping and support the run: step by step
- Install pipe supports every 5 feet on both horizontal and vertical runs.
- Install a hanger support within 6 inches of any upturn in the piping.
- Slope horizontal piping downward toward the boiler at least 1/4 inch per foot.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
More commissioning tips for boiler
Source: Ultra Series 4 boiler manual, p. 70. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.