Initial control unit start-up and settings on a Viessmann boiler: The control unit comes pre-set, but several codings must be set on site. The cascade (lead boiler) control unit runs the system and boiler section 1, and the other units run as lag boilers.
Applies to: CA3B Series 2.5 to 6.0
How to fix initial control unit start-up and settings: step by step
- Switch on the main switch and all network switches on the control units.
- Switch on the control unit. Start-up runs automatically.
- Set the language, date and time, temperature units, system layout and elevation as needed.
- Confirm. The prompt 'Do you want to make further changes' appears.
If the unit shows an error code, look it up: Viessmann Boiler codes
Models
CA3B 2.5 BoilerCA3B 3.0 BoilerCA3B 3.5 BoilerCA3B 4.0 BoilerCA3B 5.0 BoilerCA3B 6.0 BoilerCA3B Series 2.5CA3B Series 3.0CA3B Series 3.5CA3B Series 4.0CA3B Series 5.0CA3B Series 6.0Vitocrossal 300 CA3B 2.5Vitocrossal 300 CA3B 3.5Vitocrossal 300 CA3B 4.0Vitocrossal 300 CA3B 5.0Vitocrossal 300 CA3B 6.0Vitocrossal 300 CA3B Series 2.5Vitocrossal 300 CA3B Series 3.0Vitocrossal 300 CA3B Series 3.5Vitocrossal 300 CA3B Series 4.0Vitocrossal 300 CA3B Series 5.0Vitocrossal 300 CA3B Series 6.0
More commissioning tips for boiler
Source: Vitocrossal 300 CA3B service instructions, p. 32. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.