Applies to: Vitorond 200 VD2A boiler
How to fix hydrostatic pressure test before connecting the boiler: step by step
- Pipe up to the isolation valves and close them.
- Install temporary caps on the nipples for the pressure relief valve and expansion tank.
- Connect a hose to the boiler drain valve and fill slowly until the gauge reads 130 psig (896 kPa) max.
- Hold pressure for 30 minutes and do not leave the boiler unattended.
- Check all push nipples and pipe connections with a flashlight for leaks. Place paper under the cast iron block to catch minor drips from the bottom push nipples.
- After 30 minutes, open the drain valve slowly to release pressure.
- Remove the caps and install the pressure relief valve and expansion tank immediately.
If the unit shows an error code, look it up: Viessmann Boiler codes
More commissioning tips for boiler
Source: Vitorond 200, VD2A Series Installation, p. 24. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.