Viessmann Boiler: Connecting the control to the gateway
Connecting the control to the gateway on a Viessmann boiler: The supplied 3 ft (91 cm) CAT-5 cable links the boiler control LON card to the gateway RJ45 socket. The BACnet IP RJ45 connection goes into the gateway for the building network. The LON card must be installed in the control first, following the boiler control manual.
Applies to: Vitotronic 300 GW5B, GW6B and 300-K MW2C controls
How to fix connecting the control to the gateway: step by step
- Confirm the LON communication card is installed in the boiler control.
- Plug one end of the supplied CAT-5 cable into the control RJ45.
- Plug the other end into the RJ45 socket inside the gateway.
- Plug the BACnet IP RJ45 communication cable into the gateway.
If the unit shows an error code, look it up: Viessmann Boiler codes
Models
More commissioning tips for boiler
Source: Versatronik 585 and 585D BACnet IP gateway manual, pp. 7-8. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.