Rinnai Boiler: Vent termination near an openable window or door (Canada, TB-200)

Updated · by Aurora Star Tech Inc.

Vent termination near an openable window or door (Canada, TB-200) on a Rinnai boiler: Rinnai bulletin TB-200 (10/2024) changed Reference B in the I-Series Plus termination clearance tables for Canadian installs to match CSA B149.1. Older printed manuals show the old value.

Homeowner with a boiler problem? Call (647) 657-2977 or book a service call — licensed technicians across Vaughan and the GTA.

Applies to: I-Series Plus combi IP060160C to IP199199C and heat-only IP060S to IP199S, Canadian installations

Common causes of vent termination near an openable window or door (canada, tb-200)

  • Termination placed using the old Reference B value
  • Inspector flags clearance to an openable window or door

How to fix vent termination near an openable window or door (canada, tb-200): step by step

  1. Applies to direct vent (concentric and twin pipe, Table 15 Ref. B) and room-air / non-direct vent (Table 23 Ref. B) terminations.
  2. Clearance from the termination to a window or door that can be opened, Canada:
  3. Input up to 10,000 Btu/h: 6 in. (15 cm).
  4. Over 10,000 up to 100,000 Btu/h: 12 in. (30 cm).
  5. Over 100,000 Btu/h: 36 in. (91 cm).
  6. Use the boiler's rated input from the rating plate to pick the line. Move the termination if it is too close.
  7. The same bulletin softens the maintenance warning wording (annual inspection is now 'recommended'); a licensed tech still does all repairs.
Safety: Gas, electrical and refrigerant work must be done by a licensed technician. Turn off power and gas before servicing, never bypass a safety control, and always follow the manufacturer's manual for your exact model.

If the unit shows an error code, look it up: Rinnai Boiler codes

Models

I-Series Plus 150K and smaller

IP060SIP090SIP120SIP150S

I-Series Plus 175K and higher

IP175SIP199S

Source: Rinnai Technical Bulletin TB-200 (10/2024), I-Series Plus Boiler Manual Revisions for Termination Clearances and Maintenance Warning, p.1-2. Written in our own words as a summary; always check the original manual.

General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.