Rinnai Boiler: Boiler filling, air purge and commissioning
Boiler filling, air purge and commissioning on a Rinnai boiler: Commissioning must be done by a licensed professional with calibrated instruments. Fill the heating side, check leaks, and deaerate before firing. The boiler does not provide freeze protection until it is filled, purged, and supplied with power and gas.
Applies to: I-Series Plus condensing combi boilers
Common causes of boiler filling, air purge and commissioning
- Boiler not filled to minimum pressure
- Air trapped in the system
- Pump not primed
How to fix boiler filling, air purge and commissioning: step by step
- Make sure all components are installed correctly.
- Open the air vent inside the boiler.
- Power on the boiler.
- Open the fill valve on the filling circuit.
- Fill to 20 PSI (138 kPa) minimum and 30 PSI (207 kPa) maximum on the controller or gauge.
- Wait for code E430 to clear. It stays on until the boiler senses at least 13 PSI (90 kPa).
- Check the heating system for leaks.
- Deaerate the system per section 10.3.
- Purge the gas line from the meter to the boiler and prime the pump before firing for the first time.
- Do not fill the boiler unless permanent power is available.
If the unit shows an error code, look it up: Rinnai Boiler codes
Source: Rinnai I-Series Plus IP060160C installation manual, p. 68. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.