Rheem Furnace: Rotate the furnace 180 and prepare the blower shelf and jacket (downflow steps 5-7)
Rotate the furnace 180 and prepare the blower shelf and jacket (downflow steps 5-7) on a Rheem furnace: Steps shown with the furnace in downflow orientation. The junction box and door switch must be moved for the flue pipe, so follow the electrical wiring section for those.
Applies to: Horizontal conversions (downflow orientation steps)
How to fix rotate the furnace 180 and prepare the blower shelf and jacket (downflow steps 5-7): step by step
- Rotate the unit 180 degrees.
- Remove the knockouts with a hammer and flat head screwdriver.
- Pre-drill 2 holes of 1/8 in in the blower shelf for the flue pipe assembly.
- Pre-drill 3 holes of 1/8 in in the jacket for the condensate trap.
- Relocate the junction box and door switch. See the electrical wiring section.
- Re-install the elbow and couplings from step 1 in the orientation shown.
- Remove the 0.403 in drain plug from the elbow drain port and discard it.
- Install the 1/2 in yellow vinyl cap on the inducer coupling. Leave the coupling clamps loose until step 10.
- Install hose G on the collector box. Let the open end hang free until step 10.
- If the IDB coupling was removed, put it back with its exhaust-flow arrow pointing the correct direction.
If the unit shows an error code, look it up: Rheem Furnace codes
Models
96V
(-)96V060(-)96V070(-)96V085(-)96V10096VA06096VA07096VA08596VA100
96MDV
96MDV06096MDV07096MDV08596MDV100
Source: Rheem 96V installation manual, p. 35. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.