Navien General: Site and installation requirements
Site and installation requirements on a Navien general: Installation and service must be done by a qualified installer. Feedwater must come from a municipal source that meets the manual's specifications. Failing to test water quality before installing may void the warranty.
Applies to: WEC600
How to fix site and installation requirements: step by step
- Confirm the feedwater is from a municipal source within the manual's specifications.
- Test the water quality before installation.
- Mount the unit on a flat, level floor indoors.
- Keep it away from rain and the elements, from freezing locations, electric heaters, and any flammable gas or substances.
- Follow the air gap requirement for the drain line (see section 2.7, p. 20).
- Keep the inlet and outlet caps on until the unit is connected to the pipe.
If the unit shows an error code, look it up: Navien General codes
More commissioning tips for general
Source: Navien WEC600 service manual, p. 7. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.