Navien Boiler: Common vent installation requirements
Common vent installation requirements on a Navien boiler: Core rules for a shared vent system. Backflow dampers and the cascade cable are required, and the common vent is only approved for altitudes up to 4,500 ft.
Applies to: NCB700 common vent installations
How to fix common vent installation requirements: step by step
- Install a communication cable between all units in the common vent system.
- Install a backflow damper in the exhaust duct of each boiler unit. Use only the damper specified in the manual.
- Use approved PVC cement for pipe joints and elbows.
- Place the boiler units as close as possible to the vent termination.
- Use a new vent system. If an old one is reused, inspect it for punctures, cracks or blockages first.
- Support horizontal vent runs every 4 ft (1.2 m) minimum and vertical runs every 6 ft (1.8 m) minimum.
- Keep the vent termination at least 12 in (305 mm) above ground and above the highest expected snow level, or as local code requires.
- Keep at least 1 ft (30 cm) between the exhaust outlet and expected snow level, and remove snow if needed.
- Do not terminate the vent over public walkways, near soffit or crawl space vents, or where condensate or vapor could cause damage or nuisance.
If the unit shows an error code, look it up: Navien Boiler codes
Source: Navien NCB700 Installation & Operation Manual, pp. 90-91. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.