Carrier Mini-Split: Field refrigerant piping pressure and vacuum test
Field refrigerant piping pressure and vacuum test on a Carrier mini-split: Pressure test and evacuate field piping before charging. Use inert gas for the pressure test and oxygen-free nitrogen for flammable refrigerant systems. Never use air or oxygen-containing gas.
Applies to: Split systems with field piping
How to fix field refrigerant piping pressure and vacuum test: step by step
- Pressure test the low side at its design pressure and the high side at its design pressure. If the high side cannot be isolated, test the whole system at the low side design pressure.
- Hold the test pressure for at least 1 hour with no drop on the gauge. Gauge resolution must not exceed 5% of the test pressure.
- Pull a vacuum to the level in the manual, which is 500 microns or less, or the level required by local code.
- Isolate the system from the vacuum pump. The pressure must not rise above 1500 microns within 10 minutes.
- Charge by the liquid method only, and keep hoses as short as possible.
If the unit shows an error code, look it up: Carrier Mini-Split codes
Models
D5FCFAH18XAKD5FCFAH24XAKD5FCFAH36XAKD5FCFAH48XAKD5FCFAH58XAKD5FCFH18XAKD5FCFH24XAKD5FCFH36XAKD5FCFH48XAKD5FCFH58XAKD5SCHA
More commissioning tips for mini-split
Source: D5FCFA installation manual, p. 3 and p. 5. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.