Carrier Heat Pump: Clearance from combustibles for units with auxiliary electric heater
Clearance from combustibles for units with auxiliary electric heater on a Carrier heat pump: Units with an auxiliary electric heater need clearance from combustible materials.
Applies to: D5FSFAH units with auxiliary electric heater
How to fix clearance from combustibles for units with auxiliary electric heater: step by step
- Do not install the unit within 3 feet (1 meter) of any combustible material.
If the unit shows an error code, look it up: Carrier Heat Pump codes
More commissioning tips for heat pump
Source: D5FSFAH service manual, p. 2. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.