Carrier Air Handler: Refrigerant line cutting, flaring and connection
Refrigerant line cutting, flaring and connection on a Carrier air handler: Field preparation and connection of copper refrigerant lines to the air handler.
Applies to: D5FUAA refrigerant piping
How to fix refrigerant line cutting, flaring and connection: step by step
- Measure the run between indoor and outdoor units and cut the pipe slightly long, square to 90°.
- Remove all burrs with a reamer or deburring tool while holding the pipe pointing down.
- Seal pipe ends with PVC tape until flaring.
- Sheath the pipe with insulation.
- Place flare nuts on both ends facing the correct direction before flaring.
- Remove the PVC tape, clamp the flare block so the pipe extends past the form, and flare per Table 24 dimensions.
- Inspect the flare for cracks and even shape.
- Connect outdoor unit pipes first, then indoor unit. Connect low-pressure line first, then high-pressure line.
- Apply a thin coat of refrigeration oil to flared ends.
- Align the pipe centers, tighten the flare nut by hand, then torque it per Table 24 with a backup wrench.
- Wrap power cable, signal cable and piping together with binding tape, keeping the signal cable separate from other wiring.
- Thread the line set through the wall to the indoor unit.
- Bend tubing only with a correctly sized bender; do not bend more than 90° or more than 3 times.
If the unit shows an error code, look it up: Carrier Air Handler codes
Models
45MUAAQ18XX345MUAAQ24XX345MUAAQ30XX345MUAAQ36XX345MUAAQ48XX345MUAAQ60XX3D5FUAA
Source: D5FUAA installation instructions, p. 39-40. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.