Carrier Air Handler: Pressure test and evacuation of field piping
Pressure test and evacuation of field piping on a Carrier air handler: Field piping must be pressure tested with inert gas and then vacuum tested before charging. Evacuation limits apply as listed.
Applies to: Split system field refrigerant piping
How to fix pressure test and evacuation of field piping: step by step
- Pressure test the low side at its design pressure and the high side at its design pressure. If the sides cannot be isolated, test the whole system at the low side design pressure.
- Hold the test pressure for at least 1 hour with no drop on the gauge. Gauge resolution must not exceed 5% of test pressure.
- Evacuate the system to 500 microns or the lower level required by local code.
- Isolate the pump from the system. Pressure must not rise above 1500 microns within 10 minutes.
If the unit shows an error code, look it up: Carrier Air Handler codes
More commissioning tips for air handler
Source: D5FSAAH / D5FLAAH Installation Instructions, p. 7. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.