Carrier Air Handler: Flammable refrigerant field joint testing and pressure/vacuum checks
Flammable refrigerant field joint testing and pressure/vacuum checks on a Carrier air handler: Requirements for field-made refrigerant pipe connections on R454B split systems. Applies before charging and before commissioning.
Applies to: Field piping and joints on R454B split systems
How to fix flammable refrigerant field joint testing and pressure/vacuum checks: step by step
- Pressure test field piping with inert gas: the low side at its design pressure and the high side at its design pressure, or the whole system at the low side design pressure if the high side cannot be isolated.
- After removing the pressure source, hold the test pressure for at least 1 hour with no drop on the gauge. Gauge resolution must not exceed 5% of test pressure.
- Evacuate the system. Once the specified vacuum is reached, isolate the pump; pressure must not rise above 1500 microns within 10 minutes. Use the lesser of 500 microns or the value required by local code.
- Test field-made joints indoors with a detector sensitive to 5 g/year or better, at a pressure of at least 0.25 times maximum allowable pressure. No leak is allowed.
- Do not use detachable joints on the indoor side of the unit. Brazed or welded joints are allowed.
- Keep all field joints accessible for inspection before they are covered or enclosed.
- Recharge only after pressure testing with oxygen-free nitrogen. Leak test again after charging and before leaving the site.
If the unit shows an error code, look it up: Carrier Air Handler codes
Source: Carrier D5FS(L)AAH owner's manual, p. 5. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.