Weil-McLain Boiler: Slope, clearance and sealing of vent and air piping
Slope, clearance and sealing of vent and air piping on a Weil-McLain boiler: Keep vent and air piping sloped back to the boiler with no sags, keep combustible materials away from the vent, and seal wall and floor openings.
Applies to: Ultra vent and air piping
How to fix slope, clearance and sealing of vent and air piping: step by step
- Slope vent and air piping continuously toward the boiler, at least 1/4 inch drop per foot of run.
- Keep at least 3/16 inch clearance between the vent pipe and any combustible wall or material.
- Seal wall and floor penetrations following local code.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: Ultra Series 4 boiler manual, p. 71. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.