Checks before commissioning the flue gas connection on a Viessmann boiler: Confirm the flue and combustion air path is sound before the boiler is started.
Applies to: Vitodens 100-W B1HE/B1KE
How to fix checks before commissioning the flue gas connection: step by step
- Confirm the flue gas route is unrestricted.
- Confirm the positive pressure flue system is gas-tight.
- Check that the inspection port covers are secure and tight.
- Confirm the combustion air openings are open and cannot be closed.
- Confirm the flue installation follows current codes for flue systems.
- Do not commission if the flue is leaking or blocked, or combustion air is short. Poisoning from carbon monoxide can result.
- Keep combustion air vents non-closable and stop condensate drainage into them with a wind protector.
If the unit shows an error code, look it up: Viessmann Boiler codes
Models
Source: Vitodens 100-W B1HE/B1KE installation manual, p. 24. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.