Rinnai Boiler: Wire the air handler output (OPU) to the boiler
Wire the air handler output (OPU) to the boiler on a Rinnai boiler: Air handler call uses the boiler's OPU output on the zone 3 thermostat connections.
Applies to: I-Series Plus Condensing Combi Boiler
How to fix wire the air handler output (opu) to the boiler: step by step
- Connect the zone pump for the air handler to Pump 3.
- Connect the thermostat to T/T 3.
- Wire the OPU output in series with the thermostat W wire, using the normally open, common or normally closed terminal as required.
- Set parameter 50 to b to enable the air handler output.
- Set parameter 51 to the post-pump run time required (15 seconds default, 40 seconds option).
If the unit shows an error code, look it up: Rinnai Boiler codes
Source: Rinnai I-Series Plus IP060160C installation and operation manual, p. 107. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.