Navien Boiler: Wall mounting the boiler
Wall mounting the boiler on a Navien boiler: Mount the upper bracket on studs, then hang the boiler and secure the bottom.
Applies to: All NCB700 models
How to fix wall mounting the boiler: step by step
- Drill into studs and into drywall for plastic anchors; the bracket is pre-drilled at 16 in on center.
- Reinforce the wall if it is weak or framing is uneven.
- Fix the bracket level and confirm it can carry the boiler weight.
- Start one screw, check level, then install the other three.
- With help, lift the boiler above the bracket hooks and lower it onto them. Mounted this way, the back sits 5/8 in from the wall.
- Install two screws through the bottom bracket to secure the boiler.
- Leave clearance for service access.
If the unit shows an error code, look it up: Navien Boiler codes
Source: Navien NCB700 installation and operation manual, p. 16. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.