How to fix ul compliance conditions for gateway installation: step by step
- Power the gateway from a listed LPS or Class 2 supply rated for the expected temperature range.
- Use interconnecting power connectors and cable that meet local electrical code, the expected temperature range, and the gateway current and voltage rating.
- Keep the interconnecting power cable 3.05 m (118.3 in) or shorter, made of VW-1, FT-1 or better rated material.
- If the ambient is above 65 °C, install in a restricted access area that needs a key or special tool.
- Do not connect this device to a LAN segment that has outdoor wiring.
If the unit shows an error code, look it up: Navien Boiler codes
Source: Navien Modbus/BACnet Gateway Start-up Guide, p. 35. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.