Navien Boiler: Installation checklist: power, DIP switches and owner handover
Installation checklist: power, DIP switches and owner handover on a Navien boiler: Electrical and PCB DIP switch checks and owner items before handing over the boiler.
Applies to: NCB700 installation
How to fix installation checklist: power, dip switches and owner handover: step by step
- Confirm supply voltage is 110-120 V AC.
- Confirm the boiler is plugged into a properly grounded outlet.
- If hard-wired, install a power switch for maintenance access, and check electrical polarity.
- On DIP SW 2 (8 switch set), set switch 1 to ON for LP or OFF for NG, matching the gas type.
- Set switch 7 to ON if continuous boiler operation is required.
- Set switch 8 to ON if high temperature venting (CPVC or polypropylene) is installed.
- Show the owner how to clean the inlet water filter and how to shut off gas in an emergency.
- Leave the Installation & Operation Manual and User's Information Manual with the owner.
If the unit shows an error code, look it up: Navien Boiler codes
More commissioning tips for boiler
Source: Navien NCB700 installation and operation manual, p. 108-109. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.