Navien Boiler: Attaching an extension kit (in-line setup)
Attaching an extension kit (in-line setup) on a Navien boiler: Adds rack sections for more boilers in an in-line layout.
Applies to: Ready-Link Commercial rack, in-line setup
How to fix attaching an extension kit (in-line setup): step by step
- Connect the extension rack to the single frame using the fixed brackets.
- Use M10 bolts (3 in and 4 in) for the connection.
- Up to 9 extension kits (10 units total) can be assembled.
If the unit shows an error code, look it up: Navien Boiler codes
Source: Ready-Link Commercial Rack System installation guide, p. 1, p. 2. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.