Viessmann Boiler: Spring-loaded flow check valves during system fill
Spring-loaded flow check valves during system fill on a Viessmann boiler: Flow check valves must be open to fill and purge the system and closed again once it is purged.
Applies to: Vitorond 200 VD2A hydronic installations
How to fix spring-loaded flow check valves during system fill: step by step
- Open the spring-loaded flow check valves before filling the heating system.
- After the system is full and purged of air, close the flow check valves to restore flow-check operation.
If the unit shows an error code, look it up: Viessmann Boiler codes
More commissioning tips for boiler
Source: Vitorond 200 VD2A installation manual, p. 34. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.