Carrier Mini-Split: Pressure test and evacuation values
Pressure test and evacuation values on a Carrier mini-split: Values from the piping and start-up checklist. The pages disagree on the test time.
Applies to: Leak test and evacuation before charging
How to fix pressure test and evacuation values: step by step
- Pressure test with dry nitrogen to a maximum of 500 psig.
- Hold the test for at least 60 minutes (p. 25). The start-up checklist lists a 30-minute hold with a 550 psig maximum (p. 50).
- Evacuate with the triple or deep vacuum method.
- Confirm the system holds 500 microns for 1 hour.
If the unit shows an error code, look it up: Carrier Mini-Split codes
More commissioning tips for mini-split
Source: D5FSAA and D5FLAA installation instructions, p. 25, p. 50. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.