Carrier Air Handler: Connect refrigerant lines to outdoor and indoor units
Connect refrigerant lines to outdoor and indoor units on a Carrier air handler: Order of connection and torque method for flare nut joints, plus the nitrogen pressure test for brazed work.
Applies to: D5FUAA 18K to 60K, field refrigerant piping
How to fix connect refrigerant lines to outdoor and indoor units: step by step
- Connect the outdoor unit end first, then the indoor unit end.
- Connect the low-pressure line before the high-pressure line.
- Put a thin coat of refrigeration oil on the flared ends.
- Line up the centers of the two pipes, then tighten the flare nut by hand as far as possible.
- Hold the unit fitting with a backup wrench and tighten the flare nut with a torque wrench to the value in the flare nut table.
- When brazing, flow nitrogen through the lines and braze the tubing and fittings for a proper seal.
- Pressure test with nitrogen to no more than 500 psig for at least 60 minutes.
- Insulate the suction line completely, including the outdoor unit valves.
- Bundle the power cable, signal cable and piping with binding tape. Keep the signal cable separate from all other wiring.
If the unit shows an error code, look it up: Carrier Air Handler codes
Models
45MUAAQ18XX345MUAAQ24XX345MUAAQ30XX345MUAAQ36XX345MUAAQ48XX345MUAAQ60XX3D5FUAA
Source: D5FUAA installation instructions, p. 40. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.