Weil-McLain Heat Pump: Installer-built (fabricated) manifold requirements
Installer-built (fabricated) manifold requirements on a Weil-McLain heat pump: If the WM Easy-Up manifold is not used, an installer-built manifold must meet these rules: at least 2 inches of vertical distance from the closely spaced tees to the first elbow on the heat pump piping (heat trap); a Y-strainer with an 80 mesh screen, mounted flow-down or horizontal; the heat pump circulator from the accessory box with its internal check valve fitted before the circulator is installed; common system piping of 1 inch or larger.
Applies to: Heat pump installer-built manifold
How to fix installer-built (fabricated) manifold requirements: step by step
- Keep at least 2 inches of vertical run from the closely spaced tees to the first change of direction on the heat pump inlet/outlet piping.
- Install the Y-strainer with an 80 mesh screen, oriented flow-down or horizontal, to protect the heat pump heat exchanger.
- Fit the internal flow check valve into the heat pump circulator before mounting the circulator, and follow the circulator maker's guidelines.
- Use 1 inch or larger pipe for the common system piping.
If the unit shows an error code, look it up: Weil-McLain Heat Pump codes
Source: ECO HP Heat Pump – Application Guide, p. 8. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.