Weil-McLain Boiler: Wall-mounting requirements
Wall-mounting requirements on a Weil-McLain boiler: The wall must be plumb and able to carry the boiler and piping. Do not use anchors or other fasteners that are not secured into the studs.
Applies to: Wall mount installations
How to fix wall-mounting requirements: step by step
- Use the wall template to locate mounting holes and check clearances.
- On wood stud walls, use the 3/8 x 3 inch lag screws supplied, only into the studs.
- On metal stud walls, secure the bracket and spacer board with bolts and washers rated for the boiler operating weight plus piping and venting loads. Hardware is not in the kit.
- Confirm the metal studs can carry the load; some are not designed for it.
- If the wall has exposed studs, provide a backer board. The boiler cannot be leveled without a backing surface.
- Perform all procedures in the earlier sections before mounting the boiler.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: ECO Tec Series 3 boiler manual, p. 14. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.