Weil-McLain Boiler: Wall and roof penetration preparation
Wall and roof penetration preparation on a Weil-McLain boiler: How to cut and seal the openings for the vent and air pipes through the building envelope.
Applies to: Direct exhaust and direct vent penetrations
How to fix wall and roof penetration preparation: step by step
- For a sidewall penetration, cut the hole at least 0.4 in larger than the pipe diameter (7 in hole for 6 in PP or PVC; 9 in hole for 8 in PP or PVC).
- For a roof penetration, cut the hole at least 0.5 in larger than the pipe diameter (7 in hole for 6 in PP or PVC; 9 in hole for 8 in PP or PVC).
- Install a galvanized metal thimble in the pipe hole.
- Use metal cover plates at wall penetrations.
- Seal the annular space around the penetration with approved materials so combustion products cannot enter the building.
- Seal exterior openings thoroughly with exterior caulk.
- Install flashing and sealing boots sized for the vent and air pipes at roof penetrations.
- Follow local codes for isolating vent pipe through floors, walls and roofs.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: SlimFit series 3 commercial gas-fired water boiler manual, p. 33 and p. 35. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.