Weil-McLain Boiler: Vent and air pipe assembly rules
Vent and air pipe assembly rules on a Weil-McLain boiler: Assemble vent and air piping so the joints stay sealed and the pipe runs cleanly. Follow the material and adapter rules in the manual.
Applies to: All SlimFit Series 2 vent and air piping
How to fix vent and air pipe assembly rules: step by step
- Install the SlimFit vent/air adapter at the boiler vent and air connections, and add a pipe-maker reducer if the pipe is smaller than the adapter outlet.
- Check that the vent-to-adapter gasket is in place with the barbed band pointing down.
- Tighten the vent connection clamp securely, but do not over-tighten it or let the band deform or dig into the plastic connector.
- Put a locking collar on every vent and air joint.
- Permanently join PVC and CPVC joints with the correct primer and cement.
- Use sweep elbows where possible, because short-radius elbows cut allowable pipe length.
- Install a manufacturer bird screen at each vent and air termination. Buy the screen from the pipe supplier.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: SlimFit 1000-2000 Series 2 boiler manual, p. 24. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.