How to fix solvent-weld pvc or cpvc vent and air joints: step by step
- Deburr inside and outside of each pipe end.
- Chamfer the outside of each pipe end so cement spreads evenly.
- Clean all pipe ends and fittings and dry them thoroughly.
- Handle fittings and pipe carefully so the joint surfaces are not contaminated.
- Apply primer liberally to the pipe end and fitting socket.
- While the primer is still damp, apply cement in a uniform coat to both surfaces. Apply a second coat. Avoid excess cement in the socket.
- With cement still wet, insert the pipe fully into the fitting, twisting about 1/4 turn.
- Wipe off excess cement and check for a smooth bead all around the joint.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: ECO Tec series 3 boiler manual, p. 32. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.