Weil-McLain Boiler: Sidewall direct vent with separate vent and air pipes: termination location
Sidewall direct vent with separate vent and air pipes: termination location on a Weil-McLain boiler: Choose a sidewall location that meets clearances and gives clean routing from the boiler vent connection.
Applies to: SVF direct vent sidewall separate pipes
How to fix sidewall direct vent with separate vent and air pipes: termination location: step by step
- Confirm the termination meets the clearances in the direct vent location table before cutting anything.
- Keep the termination at least 12 in above grade and snow line, and keep vent and air areas clear of snow.
- Pick a spot where leaves, debris and sediment are unlikely to build up on the termination.
- Plan the boiler location so vent piping can run cleanly from the boiler connection to the sidewall termination without exceeding the maximum vent length.
- Consider plume and condensate effects on nearby surfaces and people when selecting the location.
- Keep 4 ft horizontal clearance from electrical and gas meters, regulators and relief equipment, and do not place the termination above or below them.
- For multiple boilers, follow the multiple termination layout and spacing shown for separate pipes.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: SVF 500/600 Series 1 Boiler Manual, pp. 49-50. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.