Weil-McLain Boiler: Sidewall direct vent: build the termination assembly
Sidewall direct vent: build the termination assembly on a Weil-McLain boiler: Assemble the sidewall terminations so the vent and air pipes cannot be pushed inward.
Applies to: SVF 1500-3000 sidewall direct vent (Category IV)
How to fix sidewall direct vent: build the termination assembly: step by step
- Cut the air pipe hole sized to the vent/air pipe maker's instructions.
- For combustible walls, cut the vent hole at least 3/8 in larger than the vent pipe diameter, or larger if the vent maker specifies.
- For noncombustible walls, size the opening per the vent maker's instructions.
- Install a corrosion-resistant metal thimble in the vent hole and follow local isolation codes.
- Fit corrosion-resistant stop plates (get them only from the vent pipe maker). Hole size must be just larger than the pipe diameter.
- Insert the last lengths of vent and air pipe from outside until the female shoulders rest on the stop plates.
- Secure external vent and air pipe runs up to 4 ft each with braces spaced no more than 24 in apart. Runs over 4 ft each need an insulated enclosure to prevent condensate freezing.
- Attach the exterior piping and the outward-facing vent elbow and down-turned air elbow.
- Install a bird screen in the open end of both termination elbows.
- Seal all exterior openings with exterior caulk.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: SVF Series 1 boiler manual, p. 42. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.