How to fix reinstalling the brazed plate heat exchanger and inlet manifold gaskets: step by step
- Install four new gaskets in the DHW inlet and DHW return plate connections.
- Slide the brazed plate into the rear of the enclosure with the 'This side up' label facing up.
- Lift the plate slightly to align with the DHW connections, reinstall the two Allen head screws and tighten to the torque in the torque table.
- Make sure gaskets are in good condition and aligned before tightening.
- Open the CH supply and return valves and fill the boiler. Purge all air and check every joint for leaks.
- Open the DHW cold inlet and DHW hot outlet valves, flush through a fixture and check for leaks.
- Restore gas and power per the operating instructions. The 3-way valve may be toggled to bleed air. Run the 3-way valve test (page 143).
- Reset and clear any faults that occurred during service.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: ECO Tec series 3 boiler manual, p. 157. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.