Weil-McLain Boiler: Priority operation for multiple systems
Priority operation for multiple systems on a Weil-McLain boiler: Priorities set the order in which systems are served. MAX ON TIME limits how long a priority runs before a lower priority is called. MIN ON TIME sets how long a priority runs before a higher priority or the next lower one can take over. Each priority has its own parameters.
Applies to: Single and network boilers
How to fix priority operation for multiple systems: step by step
- Select the system type for each priority; the control loads preset parameters.
- Choose CUSTOM only when the presets do not suit the system.
- Set MAX ON TIME and MIN ON TIME for each priority.
- Assign each input/output pair to a priority.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: Series 2 Advanced Manual, p. 9. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.