How to fix massachusetts side wall vent requirements: step by step
- Confirm a hard wired CO detector with alarm and battery backup is installed on the level where the boiler is installed.
- Confirm a battery or hard wired CO detector with alarm is on each additional level served.
- If installed in a crawl space or attic, the hard wired detector may go on the next adjacent floor.
- If the requirements cannot be met at completion, the owner has 30 days to comply. Install a battery CO detector in the meantime.
- Use detectors that meet NFPA 720 and are ANSI/UL 2034 listed and IAS certified.
- Mount a metal or plastic sign on the exterior at least 8 ft above grade, in line with the vent terminal. Lettering must be at least 1/2 inch and read GAS VENT DIRECTLY BELOW, KEEP CLEAR OF ALL OBSTRUCTIONS.
- Leave a copy of all venting and installation instructions with the appliance.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: CGi Series 5 Gas-Fired Water Boiler boiler manual, p. 21. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.