Weil-McLain Boiler: Leveling and placing a floor-mounted boiler
Leveling and placing a floor-mounted boiler on a Weil-McLain boiler: Place the boiler and check it is level before piping.
Applies to: Ultra Series 4 boilers
How to fix leveling and placing a floor-mounted boiler: step by step
- Set the boiler in place.
- Check that it is level and adjust the legs if needed.
- For wall mounting, use only the optional wall-mount kit from WM Technologies (see page 50).
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: Weil-McLain Series 4 gas-fired water boiler manual, p. 7. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.