Weil-McLain Boiler: Hydrostatic pressure test before gas and electrical hookup
Hydrostatic pressure test before gas and electrical hookup on a Weil-McLain boiler: Test the boiler with water before connecting gas piping or power. Use a test gauge of the right range, not the gauge shipped with the boiler. Steam boilers are tested at 45 to 55 psi. Water boilers are tested at 1-1/2 times maximum working pressure.
Applies to: EG and PEG boilers, pre-startup
Common causes of hydrostatic pressure test before gas and electrical hookup
- Leaks in the boiler or tappings
- Petroleum-based sealing compounds, which damage the boiler
How to fix hydrostatic pressure test before gas and electrical hookup: step by step
- Plug any boiler tappings or openings not in use.
- Install a test gauge with an appropriate range.
- Fill the boiler with water and vent all air.
- Pressurize to 45 to 55 psi for a steam boiler, or 1-1/2 times maximum working pressure for a water boiler.
- Do not leave the boiler unattended during the test.
- Confirm the gauge holds pressure and check all joints for leaks.
- Drain the boiler, repair any leaks at once and retest.
- Remove plugs from tappings that will carry controls and accessories.
- On first startup, check the system piping for leaks and repair at once.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: EG / PEG Series 7 Boiler Manual, p. 15. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.