Weil-McLain Boiler: Final checks before first start
Final checks before first start on a Weil-McLain boiler: Complete these checks after the system is filled and before the boiler is started. Look for leaks, make sure the vent and air piping are sound, and confirm the gas and electrical connections are correct.
Applies to: SlimFit Series 2 commissioning
How to fix final checks before first start: step by step
- Set up the control and confirm every setting is correct.
- Confirm the boiler and system are full of water and components are set for operation.
- Purge air from the system using the manual vents.
- Check all system piping for leaks and fix any leak before running the boiler.
- Fill the condensate trap with water.
- Confirm electrical connections are correct and tight.
- Inspect vent and air piping for corrosion, damage or sagging, and confirm it is installed per the manual.
- Check pressure switch sense hoses are on the correct fittings and in good condition.
- Before startup, smell near the floor and around the boiler for gas odour, and do not start if a leak is suspected.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: SlimFit Series 2 boiler manual 550-100-561/1225, p. 81. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.