Weil-McLain Boiler: Fill and test the water system
Fill and test the water system on a Weil-McLain boiler: Fill only after the water meets the chemistry limits. Check for leaks at fill and during startup.
Applies to: SVF 1500, 2000, 2500, 3000
How to fix fill and test the water system: step by step
- Close manual and automatic air vents and the boiler drain valve.
- Fill to the correct system pressure. Pressure rises when the boiler heats up.
- Keep operating pressure at or below 80% of the relief valve setting for most systems.
- Check the whole system for leaks at fill and during startup, and repair all leaks before going on.
- Add Sentinel X100 inhibitor after filling, following the container directions, then recheck the level and add more if needed.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: SVF Series 1 boiler manual, p. 85. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.