Weil-McLain Boiler: Electrical installation requirements
Electrical installation requirements on a Weil-McLain boiler: Wiring must meet N.E.C. Class 1. The boiler must be electrically grounded per NEC / ANSI/NFPA 70. Comply with NEC and any national, state or local codes. The boiler ships with controls wired except the spill switch and vent damper. Shut off power at the service entrance before making any connections.
Applies to: CGi Series 5 boilers, spark-ignited pilot
How to fix electrical installation requirements: step by step
- Turn off power at the service entrance panel before any electrical work.
- Confirm the boiler is electrically grounded as NEC requires.
- Use N.E.C. Class 1 wiring for field connections.
- Wire the spill switch and vent damper, which are not factory-wired.
- Use the boiler wiring diagrams on pages 46 and 48 for the spark-ignited pilot model.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: CGi Series 5 gas-fired water boiler manual, p. 41. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.