Direct exhaust vertical termination installation on a Weil-McLain boiler: Category IV direct exhaust through the roof or a vertical termination. Same material and joint rules as the sidewall method. Use flashing and sealing boots sized for the vent pipe. Do not exceed the maximum outside vent length shown in Figure 30, because excess exposed pipe can freeze condensate or cause failure.

Homeowner with a boiler problem? Call (647) 657-2977 or book a service call — licensed technicians across Vaughan and the GTA.

Applies to: SlimFit 1000-2000 Series 2 direct exhaust, vertical

Common causes of direct exhaust vertical termination installation

  • Condensate freezing in the vent pipe if too much pipe is exposed outside
  • Vent/air piping failure in very cold climates

How to fix direct exhaust vertical termination installation: step by step

  1. Install the vent manufacturer's SlimFit Vent Adapter and reducer (if needed) at the boiler vent connection.
  2. Slope vent piping toward the boiler at least 1/4 in per foot on horizontal runs.
  3. Support piping every 5 ft on horizontal and vertical runs, with a hanger within 6 in of any upturn.
  4. Cut the vent penetration. For combustible construction, make it at least 3/8 in larger than the pipe diameter.
  5. Install a corrosion-resistant metal thimble and isolate the pipe per local code through floors, ceilings and roofs.
  6. Install flashing and sealing boots sized for the vent pipe.
  7. Use a coupling or open-end pipe termination per the vent manufacturer's vertical termination guidelines.
  8. Install a bird screen in the open end of the termination.
  9. Keep the finished termination dimensions as shown in Figure 30.
  10. Protect and support exposed piping per the vent manufacturer for cold climates.
Safety: Gas, electrical and refrigerant work must be done by a licensed technician. Turn off power and gas before servicing, never bypass a safety control, and always follow the manufacturer's manual for your exact model.

If the unit shows an error code, look it up: Weil-McLain Boiler codes

Source: SlimFit-1000-2000 Boiler Manual 550-100-561/1225, p. 35. Written in our own words as a summary; always check the original manual.

General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.

Emergency Boiler Repair

647-657-2977