Weil-McLain Boiler: Commissioning verification checklist
Commissioning verification checklist on a Weil-McLain boiler: Confirm all commissioning items are complete before leaving the boiler. The list covers controls, water, air purge, condensate, thermostat wiring, combustion, gas input and owner handover.
Applies to: SlimFit Series 2 commissioning
How to fix commissioning verification checklist: step by step
- Confirm the control is programmed correctly and the system is filled with water and air purged.
- Confirm water chemistry and inhibitor per page 79.
- Confirm automatic air vents, if used, are opened one full turn.
- Confirm the condensate trap is filled and thermostat wiring has no stray voltage.
- Confirm burner flame and combustion are verified per page 82.
- Confirm space heating and DHW control operation, and test any field-installed controls.
- Cycle the boiler with the thermostat and confirm it starts and stops correctly.
- Confirm measured gas input and incoming gas pressure.
- Set the room thermostat and DHW aquastat as required.
- Complete the installation certificate, warranty card and leave the instructions with the owner.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: SlimFit Series 2 boiler manual 550-100-561/1225, p. 84. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.