Viessmann Boiler: Post-installation checklist for the Vitotronic 300
Post-installation checklist for the Vitotronic 300 on a Viessmann boiler: Before leaving the job, confirm the wiring, sensors and boiler coding card are right and that the control is set up for the heating circuits present.
Applies to: Vitotronic 300 KW3
How to fix post-installation checklist for the vitotronic 300: step by step
- Check that the limit capillaries and sensors are fully seated in their wells.
- Check that all electrical connections are made correctly and every connector is fully plugged in.
- Confirm the boiler coding card is inserted.
- Confirm fuse F2 is plugged in.
- Confirm the outdoor temperature sensor is mounted correctly and its cable is properly connected at the sensor and at the connector.
- Set the fixed high limit and the adjustable high limit correctly, if required.
- Label the programming unit fields to match the heating circuit allocation.
- Carry out start-up and adjustments using the Service Instructions.
If the unit shows an error code, look it up: Viessmann Boiler codes
More commissioning tips for boiler
Source: Vitotronic 300 installation instructions, p. 24. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.