Viessmann Boiler: Frame mounting and levelling the boiler
Frame mounting and levelling the boiler on a Viessmann boiler: Free-standing installation on the boiler stand or frame. The wall location for the frame, bracket and vents is not supplied and must be calculated in the field. The boiler must sit level both ways so condensate drains properly.
Applies to: Vitodens 200-W B2HB 45, 57, 160, 199
How to fix frame mounting and levelling the boiler: step by step
- Secure the boiler stand to the floor. Concrete expansion anchors are specified as Hilti KB-TZ (size illegible in source) or equivalent.
- Fasten the wall mounting bracket to the boiler mounting frame using the supplied hardware and make sure the bracket is level.
- Move the frame into position and secure it to the floor, and to the wall if needed.
- Remove the external accessories connection box cover.
- Loosen (do not remove) the screws at the bottom of the boiler.
- Remove the front enclosure panel by lifting it up and pulling it away from the boiler.
- Mount the boiler onto the mounting bracket and make sure it is secure. Install the holding bracket to the frame on top of the boiler.
- Adjust the levelling screws until the boiler is level.
- Connect the boiler to the installation fittings.
If the unit shows an error code, look it up: Viessmann Boiler codes
Models
Vitodens 200-W B2HB 45Vitodens 200-W B2HB 57Vitodens 200-W B2HB 160Vitodens 200-W B2HB 199
Source: Vitodens 200-W B2HB installation manual, p. 16-17. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.