Warming things up…Dialing in your comfort…Almost cozy…
Reliable Heating and Cooling Solutions – Quality Service, Fair Prices, Guaranteed Satisfaction!

Commissioning: Boiler tips (part 21 of 21)

Updated · by Aurora Star Tech Inc.

Short, practical technician tips on commissioning for boiler. Check each one against the manual for your exact model before acting.

Return water temperature and low-temperature systems

Weil-McLain · Low-temperature and radiant systems

Figures 16 and 17 apply only when return water is at least 130°F. Systems with low return temperature need bypass piping to prevent condensation and corrosion.

  1. Use the Figure 16 or 17 piping only for systems designed for at least 130°F return water.
  2. For converted gravity systems, radiant systems or other low-return systems, install bypass piping (page 22).
  3. If the system has radiant circuits, add piping and controls to regulate the supply temperature to them.

Review with owner at startup

Weil-McLain · SVF 1500-3000 Series 1 boiler

Points to cover with the owner at the end of startup.

  1. Review the SVF User's Information Manual with the owner.
  2. Stress the maintenance schedule in the User's Information Manual.
  3. Tell the owner to call a licensed contractor if the boiler or system behaves unusually.
  4. Tell the owner to follow the proper shutdown procedure.
  5. Schedule an annual startup at the start of the next heating season.

Sensor placement for system supply and return

Weil-McLain · Multi-boiler piping with system sensors

Supply and return sensors are strapped to the system piping away from the boiler tees.

  1. Strap the system supply and return sensors to the lines at least 6 pipe diameters from the boiler connection tees.
  2. Do not put the sensors more than 3 feet from the tees.
  3. For redundancy, install a supply and return sensor for each boiler.

Sentinel X100 inhibitor is required

Weil-McLain · ECO Tec Series 3 80/110/150/199

The ECO Tec boiler must have Sentinel X100 in the system to protect the heat exchanger.

  1. After filling as directed, add X100 aerosol following the container instructions.
  2. Let the water circulate and mix.
  3. Check the inhibitor level and add more if needed.
  4. Check the inhibitor level annually with the Sentinel test kit.

Set boiler model, altitude and fuel type first

Weil-McLain · All ECO Tec Series 3 boilers

Boiler model, altitude and fuel type are critical control settings. Wrong values can cause severe injury, death or property damage. Confirm them before adjusting any priority settings.

  1. Verify the boiler model, installation altitude and fuel type on the control.
  2. Correct any mismatch before changing priority or pump settings.

Set maintenance reminder and contractor info

Weil-McLain · Maintenance Info menu

The display shows a maintenance reminder, default 12 months. Set it up with the contractor details and reset it at each service visit.

  1. Open MAINTENANCE and enter contractor name, CP number and install date.
  2. Set the maintenance interval based on service history.
  3. At each service visit, choose RESET REMINDER to update Last and Next dates.
  4. Enter the current date and time so lockout records are time-stamped.

Set water temperatures to suit the system

Weil-McLain · All Series 2 boilers with Evergreen Pro control

Excessive water temperature can cause significant property damage in some applications. Set the control for the water temperatures the system can safely handle.

  1. Check the system's maximum safe water temperature before setting the control.
  2. Set the control to match that temperature limit.

Setup wizard options

Weil-McLain · ECO Tec control first setup

The wizard walks through setup step by step and is recommended. USE APP sends a settings file from the app for a faster setup. SKIP WIZARD skips all setup and requires manual entry of every setting, which is not recommended.

  1. Press USE WIZARD for a guided setup (recommended).
  2. To use the app, press USE APP and send the settings file from the app.
  3. Avoid SKIP WIZARD unless the full manual setup is intended.
  4. If the wizard was skipped, use RESTART WIZARD under Reset to Factory Defaults in the Boiler Settings menu, reached via the Contractor menu.

Sizing system and zone circulator flow

Weil-McLain · System and zone circulators supplied by installer

Flow in gpm equals heat load in Btuh divided by (temperature drop x 500). For a 20°F drop, flow equals MBH divided by 10. The circulator must deliver this flow against the calculated head loss.

  1. Calculate flow: FLOW = BTUH / (TD x 500).
  2. Example: 210,000 Btuh load with 20°F drop gives about 20 gpm.
  3. Find pipe size and head loss using accepted engineering methods.
  4. Select a circulator that meets the flow at that head loss.

Skipping blower calibration during the wizard

Weil-McLain · ECO Tec control, wizard blower calibration

Choosing SKIP CALIBRATION lets you continue the wizard, but the boiler will not operate until calibration is done. Run it later from the Boiler Settings screen in the Contractor menu. Calls for heat are ignored and the boiler stays in standby until calibration is complete.

  1. Open the Contractor menu (see access tip).
  2. Go to the Boiler Settings screen.
  3. Select the blower calibration option and run it.

Stability warning for floor stand installs

Weil-McLain · Pedestal floor stand installations

A boiler on a pedestal stand can be top-heavy and tip before the piping is connected.

  1. Do not leave the boiler unsupported on the stand until the flue and water pipe connections are made.
  2. Once the flue and water connections are complete, the boiler is stable.
  3. An unsupported boiler can fall and cause severe injury or death.

Startup screen - select control configuration

Weil-McLain · ECO Tec control first power-up

On first power-up the control asks for the configuration. Single Boiler is for a stand-alone boiler. On Network as Master controls the firing rate and burner-on commands for a multi-boiler network, and only one master is allowed. On Network as Shadow is controlled by the master for network heat calls and runs itself for local calls.

  1. Choose Single Boiler for a stand-alone installation and press the right arrow.
  2. For a multi-boiler network, choose Master on one boiler only and Shadow on the others.
  3. Check the boiler model on the startup screen matches the actual boiler.
  4. If the model does not match, perform a factory reset as described in the manual.
  5. Check the system and outdoor sensor status shows as expected; check sensors if not.

Steam boiler piping layout

Weil-McLain · EG and PEG steam boilers

Connection rules for steam boilers. Proper piping prevents operating faults and boiler damage.

  1. Connect the steam supply on the same end as the controls. Return may connect at either end.
  2. Install the boiler jacket before connecting return piping. Connect controls after all piping is connected.
  3. Keep at least 24 in. from the waterline to the bottom of the header.
  4. Use an offset header so it does not bend at the section tappings.
  5. For counterflow systems, connect the boiler steam supply into the top of the counterflow header (Figure 22, page 25).

System supply and return sensor placement

Weil-McLain · Ultra U-Control system temperature sensing

Two strap-on sensors ship with the boiler and can attach to pipe up to 3 inches in diameter. The supply sensor must be at least six pipe diameters but no more than 3 feet downstream of the boiler connection. The return sensor is used for display and for sensor-failure checks. For multiple boilers, the lead boiler needs both sensors.

  1. Strap the system supply sensor on the main piping at least six pipe diameters, and no more than 3 feet, downstream of the boiler connection.
  2. Strap the system return sensor on the return piping.
  3. For multiple boiler applications, wire both sensors to the LEAD boiler.
  4. Confirm the sensors are wired with thermostat wire or equivalent.

Thermostat anticipator setting

Weil-McLain · ECO Tec Series 3 all models

Thermostat anticipator is set to 0.1 A on these pages.

  1. Set the thermostat anticipator to 0.1 amps.

Use sweep elbows on all vent and air piping

Weil-McLain · All direct vent and direct exhaust installs

Short radius elbows reduce boiler performance. Sweep elbows are required on all vent and air piping, including the direct exhaust installs.

  1. Use sweep elbows for all vent and air piping.
  2. Do not use short radius elbows anywhere in vent or air runs.

Use the Setup Wizard and a preloaded system type

Weil-McLain · ECO Tec Series 3 boilers with Unity 2.0 control

The Unity 2.0 touchscreen has a Setup Wizard that walks through installation. It includes ten preloaded system types, which cuts setup time and guesswork.

  1. Start the Setup Wizard on the Unity 2.0 touchscreen.
  2. Select the preloaded system type that matches the hydronic layout.
  3. Work through each wizard screen in order to finish the setup.

Use two wrenches on water pipe connections

Weil-McLain · ECO Tec 80/110/150/199 Series 3

When tightening any pipe connection to the boiler, hold the boiler pipe with a second wrench so it does not turn. Turning it can damage the pipe or heat exchanger.

  1. Use two wrenches on every boiler pipe connection.

Vent and air pipe requirements

Weil-McLain · ECO Tec Series 3 boilers

ECO Tec needs direct venting as a Category IV boiler. Use only the vent materials and methods in this manual. Vent and air pipes can be 2 in or 3 in with an adapter for 2 in. Air intake must be 3 in PVC at the adapter. Exhaust must be 3 in PVC, PP or SS at the adapter. All elbows must be sweep elbows, not short-radius. Direct exhaust venting is possible only with the kit option.

  1. Confirm vent and air pipe size (2 in or 3 in).
  2. Use a 2 in to 3 in adapter at the boiler for 2 in venting.
  3. Check that air intake is 3 in PVC and exhaust is 3 in PVC, PP or SS at the adapter.
  4. Use sweep elbows only.

Venting fittings and vent sizes

Weil-McLain · ECO Tec 80/110/150/199 Series 3

ECO Tec boilers need Category IV venting. Use only the vent materials and methods in the manual. Vent and air pipe can be 2" or 3"; a 2" run needs an adapter. Air intake must be 3" PVC at the adapter; exhaust must be 3" PVC/PP/SS at the adapter. Use sweep elbows only, not short-radius elbows. Direct exhaust venting is possible with the kit option.

  1. Confirm the vent is Category IV-rated material and method.
  2. Use an adapter if running 2" vent.
  3. Install 3" PVC air intake at the adapter and 3" PVC/PP/SS exhaust at the adapter.
  4. Use sweep elbows on all vent and air elbows.

Verify propane conversion and blower model

Weil-McLain · ECO Tec Series 3 80/110/150/199

Boilers ship ready for natural gas only. For propane, confirm the conversion. On the 199, confirm the blower model is selected.

  1. For propane, verify the boiler was converted per page 19 before startup.
  2. On the 199, check the blower label (Figure 158, page 177).
  3. Confirm the correct model is selected on the Boiler Settings Blower Model screen.
  4. Verify this again after a factory reset, control replacement or blower replacement.

Verify propane or natural gas venturi label

Weil-McLain · ECO Tec 80/110/150/199

Each gas type uses a different venturi label. Confirm the label matches the gas and model before installing.

  1. Propane venturi has a black label marked LP.
  2. Natural gas venturi has a white label.
  3. Confirm the label part number matches the model size from the venturi table.

Verify the boiler model setting before startup

Weil-McLain · All Ultra models

The U-Control model setting must match the rating plate. A wrong model setting can cause severe injury, death or property damage. The model is also shown on the display at power-up.

  1. Read the model on the boiler rating plate.
  2. Check the BOILER MODEL setting in the contractor menu (80, 105, 155, 230, 299 or 399).
  3. Change the setting if it does not match.
  4. Confirm the model shown on the display at power-up.

Water chemistry and system cleaning for stainless heat exchanger

Weil-McLain · SVF 1500-3000 Series 1

The stainless steel heat exchanger needs system pH between 7.0 and 8.5, checked water chemistry and chemical treatment. Sediment can damage it, and make-up water adds minerals and oxygen. Use the boiler only in a closed-loop system.

  1. Flush the system with the boiler disconnected to remove sediment.
  2. Install a strainer or other sediment removal if needed.
  3. Check pH is between 7.0 and 8.5 and treat the water chemistry.
  4. Do not use petroleum-based cleaning or sealing compounds.
  5. Repair leaks right away to stop make-up water entering the system.
  6. Do not add cold water to a hot boiler.

Water chemistry for stainless steel heat exchanger

Weil-McLain · Evergreen boiler water side

The heat exchanger is stainless steel, so check water chemistry. System pH must be 7.0 to 8.5. Chemical treatment may be needed.

  1. Flush the system before connecting the boiler and install a strainer or sediment separator if needed.
  2. Do not use petroleum-based cleaning or sealing compounds.
  3. Use the boiler in a closed-loop system only.
  4. Repair leaks at once, since make-up water shortens boiler life.
  5. Do not add cold water to a hot boiler.

Wizard sequence order

Weil-McLain · SVF Series 1 Unity Wizard

The Wizard walks through boiler settings, inputs/outputs, priorities, system settings and types, output activation, priority switching, date/time and installer information.

  1. Boiler Settings: altitude, fuel, WWSD.
  2. Inputs/Outputs: usage of inputs 1-3 and outputs 1-3.
  3. Set Priorities: assign priorities 1-3 to the inputs.
  4. System Settings and System Types: keep defaults or change, and set the operating temperature type for each output.
  5. Output Activation: select AUX PUMP/OUTPUT activation when applicable.
  6. Priority Switching: set max and min times.
  7. Date/Time: set the clock for diagnostic logging.
  8. Information: set installer contact, CP#, install and maintenance dates, and maintenance notification timing.
Safety: Gas, electrical and refrigerant work must be done by a licensed technician. Turn off power and gas before servicing, never bypass a safety control, and always follow the manufacturer's manual for your exact model.

General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.

Emergency Boiler Repair

647-657-2977