Installation checklist before power-up on a Navien general: Confirm every item on the installation checklist before the unit is powered. Any item answered No needs the matching installation section fixed first. Troubleshooting is in section 6 (page 52).
Applies to: WEC600
How to fix installation checklist before power-up: step by step
- Confirm the WEC is in a suitable location and level (adjust leveling feet).
- Confirm a water bypass is installed for service.
- Check drain tubes have an air gap, length is 197 in. (5 m) or less, and height is 10 ft (3 m) or less.
- Confirm the NDI module freeze prevention drain line is installed.
- Confirm the NaviLink Lite is installed and the CIP tank is full.
- Confirm the power cord is in a properly installed, grounded outlet that meets local code.
- Confirm the system inlet is connected to the cold-water line and feedwater pressure is within specification.
- Confirm the sediment pre-filter and post carbon block filter are installed correctly.
- Confirm a check valve and expansion tank are installed for DHW recirculation or storage tank water heaters.
- Confirm piping at the sediment filter inlet and carbon block outlet is grounded, with extra grounding points on any plastic sections.
If the unit shows an error code, look it up: Navien General codes
Source: Navien WEC Series service manual, p. 24. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.