Navien Furnace: Installation checklist: power supply and condensate drain
Installation checklist: power supply and condensate drain on a Navien furnace: Electrical and drain checks to complete before startup.
Applies to: NPF700 series (all listed models)
How to fix installation checklist: power supply and condensate drain: step by step
- Confirm the supply voltage is 120V.
- Confirm the furnace is hard wired to line voltage and properly grounded.
- If a direct power connection is used, install a power switch for end-user maintenance.
- Check the polarity of the electrical connection.
- Run a condensate drain line from the furnace to a drain or condensate pump.
- On upflow and downflow models, confirm the drain trap is filled with water.
- Slope the drain line toward the drain port.
- Check that all condensate drain hoses are connected and secured.
- Install an anti-freeze device if required.
If the unit shows an error code, look it up: Navien Furnace codes
Source: Navien NPF installation and operation manual, p. 92-93. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.