Daikin Water Heater: Water piping layout requirements
Water piping layout requirements on a Daikin water heater: All water piping components are field supplied. The layout has to allow service of the cascade unit and protect the system from air, debris, and pressure swings.
Applies to: Field water piping for Mega-Q systems
How to fix water piping layout requirements: step by step
- Install a piping connection and gate valve for cleaning on the circulating and hot water piping so the cascade unit can be serviced separately.
- Install an air vent valve wherever air can collect in the water piping.
- Install a strainer rated 60 mesh or finer on the inlet piping.
- Connect the hot water supply circulation circuit through a gate valve.
- Install a closed expansion tank and safety valve in the hot water supply circulation circuit.
- Insulate all water piping and apply anti-freeze measures to all water piping.
- Do not install equipment that removes residual chlorine. Chlorine-free water can allow bacteria to grow.
If the unit shows an error code, look it up: Daikin Water Heater codes
Source: Daikin Mega-Q installation manual, p. 20 and p. 21. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.