Daikin Heat Pump: Airtight test and vacuum drying of R410A refrigerant piping
Airtight test and vacuum drying of R410A refrigerant piping on a Daikin heat pump: Done after the refrigerant piping is complete and before insulation or refrigerant charging. Use nitrogen only for the pressure test. Use tools dedicated to R410A. The vacuum pump must reach 500 microns.
Applies to: Heat source unit R410A circuit between heat source unit and cascade unit
How to fix airtight test and vacuum drying of r410a refrigerant piping: step by step
- Connect nitrogen, the refrigerant tank and the vacuum pump to the heat source unit as shown in Fig. 29. Use the service port of the liquid/gas stop valve.
- Pressurize with nitrogen to 580 psi (4.0 MPa) and do not exceed it.
- Hold the pressure for 24 hours. The test passes only if there is no pressure drop.
- If pressure drops, find and repair the leak, then repeat the airtight test.
- Evacuate from the liquid and gas stop valve service ports for at least 2 hours until the system reaches 500 microns or less.
- Hold the vacuum for at least 1 hour. If the vacuum gauge rises, the system has moisture or a leak.
- In rainy weather, after 2 hours of evacuation, break the vacuum with nitrogen to 375,000 microns, then evacuate for 1 hour more to 500 microns or less. Repeat if 500 microns cannot be reached in 2 hours.
- Keep the stop valves closed until the airtight test, vacuum drying and refrigerant charge are finished.
If the unit shows an error code, look it up: Daikin Heat Pump codes
Source: Mega-Q installation manual, p. 32-33. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.